Information:
Heavy rains in early May and early June left water in the basement. We are looking for causes and solutions.
Shingles blown from HT bell tower were replaced, but installer’s lift damaged the lawn.
An anonymous donor replaced the refrigerator in the small kitchen with a new one.
We still have unneeded John Deere spreader and plow blade attachments for sale.
Projects Completed:
Fire extinguisher system in main kitchen refurbished ($1310).
New water cooler installed in main entryway ($460).
Bringing electrical power to equipment garage dropped; too costly ($3275)
Projects Planned or In Process:
Three cross-and-flame logo mats on order and nearly complete
Parking lot repair/sealing/striping started by Del Prince Co.
Chevron window was inspected. Leak appears to be result of faulty installation.
Switching telecommunication services to Time Warner from Verizon put on hold.
Expanding small double door room approved by Trustees. Capital Fund will pay.
Church Council Decision Needed:
Trustees approved mounting large wood decorative structure from HT on Family Room wall PENDING Church Council approval and selection of location.